FORMULA · COST

Subtotal

Subtotal = Materials + Labor + Equipment + Legal

Direct cost total before overhead, profit, and taxes. Every input is user-entered — ConstrCalc® never inserts a hidden line item.

Details
FORMULA · COST

Overhead

Overhead = Subtotal × (Overhead% ÷ 100)

The share of business operating cost (office rent, admin, insurance, marketing) allocated to this project. You choose the percentage; ConstrCalc® never assumes one.

Details
FORMULA · COST

Profit

Profit = (Subtotal + Overhead) × (Profit% ÷ 100)

Contractor margin computed on top of Subtotal + Overhead, matching most professional bidding conventions.

Details
FORMULA · COST

Grand Total

Grand Total = Subtotal + Overhead + Profit + Taxes

The final project figure produced by ConstrCalc®. Every term is either a user input or a deterministic derivation of user inputs.

Details
FORMULA · AREA

Cost per ft²

Cost per ft² = Grand Total ÷ Area (in ft²)

Per-unit metric for comparing projects. Deterministic — never an average, never a prediction.

Details
FORMULA · AREA

Cost per m²

Cost per m² = Grand Total ÷ Area (in m²)

Per-unit metric in metric units. Uses the deterministic ft² ↔ m² constant (× 0.092903).

Details
FORMULA · AREA

Cost per Floor

Cost per Floor = Grand Total ÷ Number of Floors

Straight-line distribution across floors. Assumes equal floor cost — no weighting.

Details
FORMULA · TIME

Cost per Month

Cost per Month = Grand Total ÷ Project Duration (months)

Straight-line monthly distribution over the project timeline. Useful for cash-flow planning.

Details
FORMULA · MEASUREMENT

ft² ↔ m² Conversion

m² = ft² × 0.092903
ft² = m² × 10.7639

Deterministic imperial ↔ metric area conversion using the internationally accepted constant.

Details
FORMULA · MEASUREMENT

Acre ↔ Hectare

hectare = acre × 0.404686
acre = hectare × 2.47105

Land-scale area conversion between US/UK and metric units.

Details
FORMULA · MEASUREMENT

Tsubo · Ping · Pyeong

1 tsubo = 3.30579 m²
1 ping = 3.30579 m²
1 pyeong = 3.30579 m²

East-Asian traditional area units (Japan, Taiwan, Korea) — all defined as 6 × 6 shaku (Japanese foot). Same size, three names.

Details
FORMULA · MISC

Contingency Line

Contingency = user-entered line item (typically 5–10% of project scope)

ConstrCalc® does NOT auto-add contingency. If you want a reserve, enter it as a Legal / Additional line item or increase your Overhead percentage.

Details