EXPRESSION
Cost per Month = Grand Total ÷ Project Duration (months)
DESCRIPTION
Straight-line monthly distribution over the project timeline. Useful for cash-flow planning.
VARIABLES
| Symbol | Meaning |
|---|---|
| Grand Total | final project figure |
| Project Duration | the number of months you entered on Project Info |
WORKED EXAMPLE
Grand Total $26,565 · Duration 6 months Cost per Month = 26,565 ÷ 6 = $4,427.50
NOTES
Real-world spend is rarely uniform (foundation-heavy early, finish-heavy late). This is a planning average.